With the rapid development of modern livestock and poultry industry, waste treatment and resource utilization has become an important topic. Jiangxi Province is a typical agricultural province, aquaculture development potential is huge, also facing the dual pressure of organic waste treatment and environmental protection. In order to effectively solve this problem, the project owner joined hands with China Sea Environment to jointly promote the resource utilization project of livestock and poultry breeding waste in Jiangxi county. The project not only helps the local reduce environmental pollution, but also promotes the healthy and green development of livestock and poultry farming in the county, achieving a win-win situation of economic and ecological benefits.




Project introduction


Jiangxi livestock and poultry waste resource utilization project adopts a centralized treatment mode, the construction of a centralized treatment center, the feces generated by 5 million laying hens, adopt a centralized collection, transportation, storage, treatment, NCS intelligent molecular membrane fermentation system as the main treatment technology, equipped with front-end mixing equipment, transportation equipment, so as to achieve "feces do not fall".


For this project, China Sea Environment provides the whole process of consulting, design, technical support and equipment supply services, with a total of 21 sets of 300m³ NCS intelligent molecular membrane fermentation system, the use of high temperature aerobic fermentation process, with laying chicken manure as the main fermentation raw material, with powder straw as the auxiliary material, can produce 100,000 tons of organic fertilizer every year.


图片


The whole process of building a centralized processing center


Zhonghai Environment provides full consulting, design, equipment supply and technical services




Site selection


Construction site


Around the county farms, select suitable sites and build centralized treatment centers.


图片




Safe transportation of equipment


Arrive on time


The NCS intelligent molecular membrane fermentation system of China Shipping Environment was delivered on time, safely transported to the scene, and the package was intact.


图片


Civil construction


Fermentation tank construction


The ground is hardened, and the fermentation tank is constructed according to the design scheme.


图片


Design a suite of equipment


"Dirt never falls"


The professional and technical personnel of China Sea Environment design front-end mixing equipment and conveying equipment according to the needs of the owners, so as to achieve "no landing of manure".


图片


Ready for fermentation


The material enters the tank


Aeration pipe is installed at the bottom of the fermentation tank, bedding material is laid, and the mixed material is transported to the fermentation tank by transport vehicle.


图片


Start fermentation


Covering fermentation film


Cover the fermentation film, seal the edge and start fermentation.


The NCS intelligent molecular membrane fermentation system has efficient and stable operating performance, and the intelligent control system can realize automated management, greatly reducing the need for manual intervention and further reducing operating costs. Unique three-layer membrane design, environmental protection odor, can achieve emission reduction and carbon fixation.


图片




In fermentation


Steaming hot


Visible to the naked eye, the fermentation site is steaming hot, the fermentation temperature reaches 65℃, and the eggs in the materials can be killed by high temperature, and the degree of harmfulness is as high as 97%. It is expected that the fermentation can be completed in about 20-25 days to form a nutrient-rich organic fertilizer.


图片


In the construction process of this project, because of the professional project team and rich construction experience, in the face of the challenges such as tight construction period and heavy tasks, the members of the China Sea Environmental team, with superb technology and rigorous attitude, actively solve the problems in the construction process, to ensure the safety, efficiency and quality of equipment installation and commissioning, according to the needs of the owner, quality and quantity. Complete the installation task in advance. The project owner spoke highly of our team's work and sent a special letter of thanks. In the future, we will continue to improve our professional quality and service level, to provide customers with more quality and efficient products and services.


TOP

400-805-3612

sinoocean2010@163.com

No. 36 Jinshui Road, Laoshan, Qingdao City

  • WeChat

  • Video Number

  • Tiktok

Copyright © 2023-2024 Qingdao Zhonghai Environmental Engineering Co., Ltd. Record number:鲁ICP备20013595号

Website Map